Springbank Road, Clapham Upgrade

Project Update – May 2017 

The detailed design plans have now been finalised and DPTI have commenced works which are anticipated to take 3-4 months to complete (weather depending).

Springbank Road

Project Update - March 2017

The $2 million Springbank Road Upgrade Project includes the installation of a painted median, pedestrian refuges and indented parking and bus bays (providing up to 63 carparks) and is being undertaken by the Department of Planning, Transport and Infrastructure (DPTI) in liaison with Council. 

Council undertook consultation in February/March 2016 with over 6,000 residents on the proposed scheme including the traffic management proposals for the Clapham/Panorama local areas with general support for the proposed painted median scheme as detailed in a report presented to Council at its 14 June 2016 meeting.

Since June 2016 DPTI have been developing the detailed design for the scheme to enable construction to commence at the earliest opportunity. As part of this process DPTI have recently engaged with the local residents of Springbank Road to seek further feedback particularly in relation to the following design amendments that have been necessary since the concept design stage which formed part of the original joint DPTI/Council community consultation process early 2016:

Key modifications made include:

  • Freeling Crescent, Vancouver Avenue and Morshead Street are now proposed to be restricted to a left in and left out only arrangement.
  • Increased length of the proposed protected right turn lane from Springbank Road into Kent Road (contributing to the left in/left out restriction proposed for Vancouver Avenue).
  • Removal of two bus bays (bus stops relocated/removed) near View Street and Toronto Avenue.
  • Removal of targeted car parking bays.

DPTI have just completed consultation with residents and property owners on Springbank Road on these modifications.

A number of bus stops are to be relocated and two bus stops removed as part of rationalising the number of bus stops along Springbank Road and the fact that the bus stops must be indented as part of this proposal to ensure that traffic is not held up when a bus is stopped at a stop (currently motorists are able to pass a waiting bus adjacent the kerb). The revised distance between bus stops is generally within DPTI’s maximum distance requirements of less than 400-500 metres between stops. 

DPTI have advised that these works need to be substantially completed prior to June 2017 with construction to commence in March/April 2017. 

DPTI have also confirmed that the resealing of Springbank Road is likely to form part of the project albeit given road sealing needs to be undertaken in periods of warmer weather, the seal and associated linemarking is likely to be undertaken September/October 2017 after the winter season.

To minimise community disruption, it is proposed to bring forward Council’s asset renewals for footpaths and kerbing along Springbank Road such that the existing bitumen footpath on the southern side of the street (between Strathcona Avenue and Goodwood Road) and also the complete kerb along the extent of the works is completed as part of the indented parking scheme. This would coordinate the asset renewals within Springbank Road at the same time as the construction of the indented parking thus presenting a completed streetscape avoiding the need to revisit and cause further disruption in a few years time. 

The project will be beneficial in improving road safety, making it easier for pedestrians to cross the road with the provision of 3 additional pedestrian refuges, the provision of a full time bike lane, the installation of protected right turn lanes into side streets (which can also be used for storage for residents turning into and out of their properties).  Such a scheme has been used in numerous places around Adelaide and has proven road safety benefits in terms of reducing crash numbers. 

The following is provided which provides a summary of the amendments be considered to address the results of DPTI’s recent engagement exercise with residents of Springbank Road:

  • An additional indent carpark be provided
  • Four indent parks to be removed to retain trees at four different locations
  • Consideration of the relocation of the bus stop proposed to be relocated west of Oxford Circus to outside number 9 to avoid the possible removal of a significant tree and also place the bus stop in a more appropriate location to provide for passengers accessing the bus stop (via a pedestrian refuge)
  • Provision for cyclists to allow south-north movements from Freeling Crescent to Eliza Place
  • Minor linemarking improvements to improve delineation at Price Avenue/Springbank Road/Catherine Street
  • Resurfacing works of Springbank Road to be strongly considered as a separate project (cannot be committed by DPTI at present).

The above information was reported to Council at its meeting of 28 February 2017.

28 February 2017 Full Council Agenda.pdf(18412 kb)

DPTI can be contacted on 1300 794 880 or via email DPTI.CommunityRelations@sa.gov.au for further updates on the project. 

Project Update - November 2016

The Department of Planning, Transport and Infrastructure (DPTI) have been advised of Council's resolution in support of the full painted median scheme option for the Upgrade of Springbank Road.  

The Springbank Road Upgrade Project is a DPTI delivered project so detailed timeframes on when construction is likely will be subject to DPTI delivery resources and timescales. The latest update Council has received from DPTI on their progress with the scheme is that the detailed design process is currently ongoing and site works are likely to commence early in 2017. DPTI can be contacted on 1300 794 880 or via email DPTI.CommunityRelations@sa.gov.au for further updates on the project. 

In relation to potential road safety improvement works in the local Clapham area to accommodate improved safety for bus passage, Council has completed investigations and consultation into potential local parking amendments to Boothby Street/Toronto Avenue and Boothby Street/Strathcona Avenue and kerbline alterations to Boothby Street/Strathcona Avenue. Feedback is being considered and taken into account during development of detailed design for the alterations, further information will be available shortly.

Consultation Details

The community consultation to provide feedback on your preferred option for the upgrade of Springbank Road finished on Thursday 24 March 2016. The feedback was presented to Council in June. 

Thank you to everyone who provided feedback. 

At a meeting on 14 June 2016 Council considered the feedback from the community and resolved: 

  1. That Council notes the results of community consultation detailed in this report.
  2. That Council notes the work of the combined Project Working Group (comprising local community representatives, Department of Planning, Transport and Infrastructure (DPTI) and Council staff) and thanks them for their assistance in assessing options for upgrading Springbank Road and addressing traffic concerns in Clapham/Panorama.
  3. That Council writes to the Department of Planning, Transport and Infrastructure indicating its support for Option 1 - Full Painted Median Scheme, (including indented parking) for the upgrade of Springbank Road.
  4. That Council authorises Administration to formally write to the DPTI advising them of the results of the community consultation and Council’s decision in support of Option 1 - Full Painted Median Scheme (including indented parking) including confirmation of Council’s commitment to fund up to $400,000 of the overall costs for the scheme.
  5. That Council notes that any final decision on whether upgrading of Springbank Road will proceed will be made by DPTI in consultation with Council having regard to technical merits, available funding and community feedback.
  6. That Council notes that a capital contribution of up to $400,000 will be required to enable the selected option to proceed.
  7. That Council authorises Administration to undertake local community consultation in relation to the proposed road safety improvement works in the local Clapham area as outlined in this report.
  8. That Council authorises Administration to progress investigations and local community consultation in relation to the potential relocation of the Bus Terminus from Boothby Street to Kent Road as outlined in this report. Council notes that costs associated with locating the bus terminus to Kent Road are not currently included within the current construction estimates and may require additional funding, subject to further detailed design and estimates.
  9. That funding of up to $400,000 for the Springbank Road Safety Improvement Scheme and $30,000 for Clapham Area Local Traffic Improvements be included in the draft 2016/17 Capital Works Program.

A copy of the report and minutes is available below:

12 June 2016 Full Council Agenda

12 June 2016 Full Council Minutes

As a result of the recently announced State Government funding of $1.6 million dollars to upgrade Springbank Road at Clapham, the Department of Planning, Transport and Infrastructure and City of Mitcham have been working in collaboration with the community based Project Working Group to develop preferred options for consultation with the community.

Council now seeks your feedback on your preferred option for the upgrade of Springbank Road. The options for the upgrade of Springbank Road are:

Option 1
Full painted median (including indented parking)

Option 2
Traffic lights at Eliza Place and Kent Road, with four lanes of traffic and clearways between 7am-10am and 3pm-7pm

Option 3
Not to upgrade Springbank Road should a general consensus not be able to be reached through the consultation process.

Option 1 – Full Painted Median

This option involves the installation of a full painted median extending between Goodwood Road and Belair Road with associated indented parking along Springbank Road. This option consists of:

  • 2 lanes each 3.3 m wide (1 east, 1 west)
  • 2.7 m wide dedicated right turn lanes
  • 5 pedestrian crossing points (1 signal controlled)
  • On‐road cycle lane
  • Indented (verge) parking bays at feasible locations
  • Indented bus stops

This upgrade option provides the following key benefits: 

  • A uniform traffic flow without reducing flow capacity and prevents the dangerous and illegal practice of overtaking on left side.
  • Addresses concerns raised of rear end collisions through creation of right turn lanes
  • Significantly increases pedestrian safety and connectivity through provision of pedestrian refuges (1 signalised, 4 median refuges)
  • Improves cyclist safety though provision of bicycle lanes
  • Reduces the chance of head on collisions by separating opposing traffic flows
  • Maintains and enhances access to private properties
  • Provides indented bus bays at feasible locations
  • Provides indented parking bays at feasible locations

However this upgrade option does not address community concerns of:

  • Access onto Springbank Road at Eliza Place and Kent Road remain predominantly unchanged
  • Existing bus routing to avoid turning right onto Springbank Road at Eliza Place and Kent Road) remain unchanged

An example of the type of traffic improvements included in this upgrade option can be seen in the extract

Option 1 Springbank Road Clapham Upgrade Concept Plan(5968 kb) (Plans supplied by Department Planning, Transport and Infrastructure)

Option 2 – Traffic Lights at Eliza Place and Kent Road

This option involves the installation of traffic lights at Eliza Place and Kent Road, with four lanes of traffic and clearways between 7am-10am and 3pm-7pm. Again the option extends between Goodwood Road and Belair Road and consists of:

  • Fully signalised intersection at Springbank Road / Eliza Place and Springbank Road / Kent Road
  • 4 lanes each 3 m wide (2 east, 2 west)
  • 5 pedestrian crossing points (3 signal controlled, 2 median refuges)
  • No parking clearway (7 am‐10 am and 3 pm‐7 pm)
  • Restricted right turns during peak times:
    • Into Eliza Place and Kent Road from Springbank Road
    • In / out Vancouver Avenue and Freeling Crescent

This upgrade option provides the following key benefits: 

  • Right turn onto Springbank Road from Eliza Pace and Kent Road improved (particularly during peaks)
  • Allows safe right turn egress for buses from Eliza Place and Kent Road into Springbank Road resolving community concerns around excessive buses in local streets due to avoiding these manoeuvres
  • Provides safer egress onto Springbank Road from Eliza Place and Kent Road for all traffic
  • Traffic performance of Springbank Road not unduly impacted
  • Provides more orderly traffic flow without reducing capacity
  • Improves pedestrian safety and connectivity through provision of pedestrian refuges (3 signalised, 2 median refuges)

However this upgrade option does have the following disadvantages:

  • Concerns in relation to rear end collisions when turning right from Springbank Road are not improved
  • No room is available for dedicated cycling lanes
  • Provision of narrow 3m width vehicle lanes
  • Permanent “No Stopping at any time” parking restrictions would apply adjacent to traffic signals
  • Parking bans (clearway) during peak hours would apply for the length of road
  • No right turn from Springbank into Eliza Place and Kent Road during peak hours would have to apply (needed to ensure traffic flow not unduly impacted)
  • No right turn in/out Vancouver Avenue (needed to ensure traffic flow not unduly impacted)
  • No right turn in/out of Freeling Crescent (needed to ensure traffic flow not unduly impacted)

An example of the type of traffic improvements included in this upgrade option can be seen in the extract below: 

Option 2 Springbank Road Clapham Upgrade Traffic Lights at Eliza Place and Kent Road

Option 2 Springbank Road Clapham Upgrade Concept Plan(6275 kb) (Plans supplied by Department Planning, Transport and Infrastructure)

Option 3

Not to upgrade Springbank Road should a general consensus not be able to be reached through the consultation process.

Questions and Answers 

Q & A on the Springbank Road Clapham Upgrade(61 kb)

Find us on FacebookTwittereNews
Contact:
City of Mitcham -ABN 92 180 069 793
131 Belair Road, Torrens Park SA 5062
T: +61 8 8372 8888 | F: +61 8 83728101
E: mitcham@mitchamcouncil.sa.gov.au
Last date modified: 2017-09-26T04:20:15
SA Councils MapsSnap Send Solve
Navigation