Price Avenue Clapham Footpath Upgrade and Streetscape

Council is planning to upgrade the footpath and streetscape along Price Avenue, Clapham – eastern side (between Kinross Avenue and Springbank Road) and Springbank Road service road, Clapham – northern side (between Price Avenue and Railway Line). Construction is planned for the 2019/2020 financial year.

The footpaths will be upgraded from asphalt to permeable concrete block pavers. As part of the footpath works, Council will reconstruct existing asphalt driveways with concrete block paving.

For the Report and Council Resolution view the Agenda and Minutes.

Proposed Works

Content Image

Price Avenue Upgrade

The streetscape upgrade works will include the removal of 23 non-regulated trees along the railway corridor and plantings of new trees, which are better suited to the location.

Content Image

Price Avenue Concept Plan

Price Avenue functions as a north-south connection for both commuters and recreational cyclists predominantly using the existing on-road bicycle lanes. This forms part of the broader Belair to City Bikeway. Council has allowed for and considered the future potential alignment of the Proposed Belair to City Bikeway adjacent to the railway corridor as part of the footpath and streetscape upgrade

When can you expect works to commence?

Stage 1 of the Price Avenue footpath upgrade, between Wattlebury Road and Kinross Avenue, commenced in early December 2019 and is scheduled for completion in January / February. Stage 1 of the works included the upgrade of the intersection of Wattlebury Road and Price Avenue. These works included the installation of new pedestrian ramps to provide safer crossing points. Line marking will be installed to better delineate the intersection for motorists, pedestrians and cyclists.

The proposed timeframe of upcoming works are:

  • Wattlebury Road and Price Avenue Intersection Line marking – January / February
  • Tree Removals – January / February
  • Footpath Construction – February / March
  • Tree Planting – April / May

If you would like to meet with Council staff onsite to discuss the above upcoming works a meeting has been scheduled for Tuesday 14 January 2020 at 5pm at the intersection of Price Avenue and Bellavista Avenue.

For more information regarding the construction works, in particular, community safety during works, and some frequently asked questions click here

If you require any further information on the upcoming works please contact Council directly via email mitcham@mitchamcouncil.sa.gov.au or on 8372 8888.